The Yurralyi Maya Pipeline is a transmission pipeline owned by Hamersley Iron Pty Ltd.
The lateral was built in 2010. It is a 10 inch diameter pipeline that is 1.2km long. Its operating pressure is 10.2Mpa MOAP. The Yurrakyi Maya Pipeline is currently a non-scheme pipeline, and is subject to the access regime for non-scheme pipelines under Chapter 6A of the NGL and Part 23 of the NGR. On 20 June 2019, the ERA granted a five-year Category 1 and 2 exemption under Part 23 of the NGR for the Yurrakyi Maya Pipeline.
