The Canningvale Lateral Pipeline is a distribution pipeline located in South-West WA.
The lateral was built in 2000. It is an 8" (22cm) diameter pipeline that is 96 km long. Its operating pressure is 0.45Mpa MAOP. The Canningvale Lateral Pipeline interconnects with the Parmelia Gas Pipeline mainline and is a single shipper pipeline. The Canningvale Lateral Pipeline is a non-scheme pipeline, and is subject to the access arrangements for non-scheme pipelines under Chapter 6A of the NGL and Part 23 of the NGR. On 8 May 2023, the ERAWA granted a five-year Category 2 and 3 exemption under Part 23 of the NGR for the Canningvale Lateral Pipeline.
